State Route 1 - Interchange at SR 10 and SR 96 - Rutherford County

Construction Timeline

State Route 1 (Broad Street) and (SR 96/SR 10) Memorial Blvd./Old Fort Parkway, Murfreesboro


  • Phase 1       February 2014  -  March 2015
  • Relocate utilities
  • Shift lanes on Memorial Blvd. and install temporary paving on Memorial
  • Construct ramps on Memorial Blvd.
  • Construct walls and begin working on Lytle and College Street
  • Shift traffic on Broad Street to the west (December 2014) to build east side of Broad Street

 

  • Phase 2      April 2015  -  December 2015
  • Reconfigure traffic pattern on Memorial Blvd.
  • Construct ramps on Memorial Blvd.
  • Construct walls and finish construction on College Street, the west side of Broad Street, and Broadmore Blvd.

 

  • Phase 3      September 2015  -   May 2016
  • Grading
  • Construct bridge walls and the actual bridge
  • Install decorative concrete, traffic signals, landscaping and final pavement markings

May 31, 2016 – Project Complete