The Latest on the Henley Project Henley Update, May 21, 2012: Work continues on Knoxville’s Henley Bridge rehabilitation project. On the south end, the cap concrete pour on Pier #7 is complete and beams are being set from Abutment B to Pier D. Re-construction and repairs at span #6 also continues in this area. On the north end, the remaining columns and caps are being completed at Span #1 and #2 along with ongoing re-construction and repairs at Pier #1 and #2. The lane shifts on Neyland Drive remain in place in order to allow for the repairs and re-construction at Span #1, Span #2 and Pier #2. These lane shifts will remain in place until August 17th. For more information on the Henley Bridge project, please visit our website, at www.tn.gov/henley. You can also follow us on twitter, at @HenleyBridge.
|