Henley Update, May 21, 2012:

Work continues on Knoxville’s Henley Bridge rehabilitation project.

On the south end, the cap concrete pour on Pier #7 is complete and beams are being set from Abutment B to Pier D.  Re-construction and repairs at span #6 also continues in this area.

On the north end, the remaining columns and caps are being completed at Span #1 and #2 along with ongoing re-construction and repairs at Pier #1 and #2.

The lane shifts on Neyland Drive remain in place in order to allow for the repairs and re-construction at Span #1, Span #2 and Pier #2.  These lane shifts will remain in place until August 17th.

For more information on the Henley Bridge project, please visit our website, at www.tn.gov/henley. You can also follow us on twitter, at @HenleyBridge.


WHAT WE'RE DOING
  • Contractor: Britton Bridge, LLC, Mt. Juliet, Tennessee
  • Amount: $24,696,969.47
  • Henley Bridge Closures: No interruptions
    to vehicle/pedestrian traffic before January 3, 2011
  • Completion in Entirety: June 30, 2013
  • Bonuses:
    • Completed by 12-31-12---$1,000,000
    • Completed by 2-15-13---$750,000
    • Completed by 3-31-13---$500,000
    • Completed by 5-15-13---$250,000
  • Contract and Addendums: (pdf)  CNJ287, Addendum 1, Addendum 2, Addendum 3, Addendum 4