Henley - A Historic Connection

Project Cameras

Project Videos

The Latest on the Henley Project

Henley Update, February 10, 2012:

Work on the Knoxville Henley Bridge continues. Substructure construction is ongoing at the north and south ends of the project. Repairs are also ongoing at these locations. Repair work has been initiated at span #6 and span #2, with the erection of new substructure components upcoming. New bridge components are now visible at span #1 as work continues in this area. Excavation of the north abutment will begin in the near future with abutment construction to follow.

Remember, for more updates on the Henley Bridge project, visit our website, at http://www.tdot.state.tn.us/henley/. You can also follow us on twitter, at @HenleyBridge.

WHAT WE'RE DOING
  • Contractor: Britton Bridge, LLC, Mt. Juliet, Tennessee
  • Amount: $24,696,969.47
  • Henley Bridge Closures: No interruptions
    to vehicle/pedestrian traffic before January 3, 2011
  • Completion in Entirety: June 30, 2013
  • Bonuses:
    • Completed by 12-31-12---$1,000,000
    • Completed by 2-15-13---$750,000
    • Completed by 3-31-13---$500,000
    • Completed by 5-15-13---$250,000
  • Contract and Addendums: (pdf)  CNJ287, Addendum 1, Addendum 2, Addendum 3, Addendum 4