Henley Update, May 17, 2013:

Work continues on Knoxville's Henley Bridge.

Barrier rail construction continues on the north approach.  On the river, Pier #5 cap construction has begun.  Pier #3 reconstruction continues, and at Pier #4 concrete forms are ready to be set.

Barrier rail has been poured on the east side of the south approach, and the west side concrete pour is forthcoming.  Neyland Drive will continue to have temporary lane closures during daytime work operations for overhead construction on the north spans.  The Greenway will also have temporary closures if work is being performed above it.  The status of the Greenway can be followed daily on twitter, at @HenleyBridge.

For more information on the Henley Bridge project, please visit our website, at www.tn.gov/henley.

NEWS RELEASES

Note: These links are to major Henley Bridge releases. For all TDOT releases on the Henley Bridge go to: http://news.tn.gov/taxonomy/term/39 and search Henley Bridge.