Skip to Content

Project Update

Improving 66 Facts

The speed limit through Phase 3 is now 35 mph.
It will remain in effect for the duration of the project (December 31, 2015).


Phase 2 – Douglas Dam Road (SR-139) to south of the I-40 Interchange:

Phase 2 is Complete!


Phase 3 - Boyds Creek Highway (SR-338) to Douglas Dam Road (SR-139):

Motorists should expect alternating northbound lane closures on SR-66 from about Knifeworks Lane to the north end of the bridge Monday (5/18) through Wednesday (5/20) between 9am and 3pm for crews to remove and relocate the portable concrete barriers.

Crews continue working on the bridges.  Presently they are adjusting the hangers for the utilities under the bridge (pictured below).  Installation of the 72” concrete storm drain along the southbound lanes continues, as well. In the coming weeks, crews are preparing to pave sections of the new outside lanes.

Short duration traffic stops should be expected daily throughout the project as crews move equipment and materials in and out of the work zone (and patch potholes).  If you have any questions regarding the project, please call us at 865.429.4509.  As always, please use extreme caution and reduce speed  through the work zone.

Updated: 05/18/2015



 
  Installing 72 inch storm drain on Phase 3. Installing new waterline on Phase 3.
 
  Placing concrete for new parapet on the southbound bridge of Phase 3.
Preparing to install temporary containment to repaint steel beams on the southbound bridge for Phase 3.
 
  Installing new stormdrain pipe on Phase 3. More basestone and curb and gutter construction is in progress for the new southbound lanes.