PAST EVENTS
Final Environmental Impact Statement (FEIS) approved by Federal Highway Administration and Consultant Design Firms began field surveying on each projects
July 2002
Surveying Completed, Preliminary Plans begun on all projects
February 2003
Design Hearings Conducted
- July 22, 2003—Section 1 (HMB Professional Services)
- May 11, 2004—Section 2 (Continental Engineering)
- June 14, 2004-Section 3 (PBS&J Engineering and Planning)
- June 15, 2004—Section 5 (Palmer Engineering)
- June 17, 2004—Section 4 (Barge, Waggoner, Sumner & Cannon, Inc.)
Right-of-Way Plans Completed
- Right-of-Way Appraisals and Acquisitions finished for Sect 1 and 5
- September 2007—Section 4
- January 2008—Section 1
- March 2008—Section 5
- January 2009—Section 2
- July 2009—Section 3
Let to Construction
- October 2009—Section 4 (Phase 1)
FUTURE EVENTS
- Right-of-Way Appraisals and Acquisitions underway for Section 3
- Turn in final construction plans for letting process for Sections 1,2,3, 4 (Phase 2), & 5