I-69 Segment 7-Dyersburg, TN To Fulton, KY

Status Report:


PAST EVENTS

Final Environmental Impact Statement (FEIS) approved by Federal Highway Administration and Consultant Design Firms began field surveying on each projects

July 2002

Surveying Completed, Preliminary Plans begun on all projects

February 2003

Design Hearings Conducted

  • July 22, 2003—Section 1 (HMB Professional Services)
  • May 11, 2004—Section 2 (Continental Engineering)
  • June 14, 2004-Section 3 (PBS&J Engineering and Planning)
  • June 15, 2004—Section 5 (Palmer Engineering)
  • June 17, 2004—Section 4 (Barge, Waggoner, Sumner & Cannon, Inc.)

Right-of-Way Plans Completed

  • Right-of-Way Appraisals and Acquisitions finished for Sect 1 and 5
  • September 2007—Section 4
  • January 2008—Section 1
  • March 2008—Section 5
  • January 2009—Section 2
  • July 2009—Section 3

Let to Construction

  • October 2009—Section 4 (Phase 1)

FUTURE EVENTS

  • Right-of-Way Appraisals and Acquisitions underway for Section 3
  • Turn in final construction plans for letting process for Sections 1,2,3, 4 (Phase 2), & 5

If you would like to comment on this project email:  TDOT.Comments@tn.gov