CURRENT PROJECT EVENTS:

2011:

2nd Qtr: The Environmental Consultant submits the Final EIS to TDOT for review and approval.

3rd Qtr:  TDOT submits the Final EIS to Federal Highway Administration for review and approval.

4th Qtr: Receive approval on the Final EIS from the Federal Highway Administration.