From Millington to Dyersburg, Tennessee in Shelby, Tipton, Lauderdale, and Dyer Counties.
CURRENT PROJECT EVENTS:
2011:
2nd Qtr: The Environmental Consultant submits the Final EIS to TDOT for review and approval.
3rd Qtr: TDOT submits the Final EIS to Federal Highway Administration for review and approval.
4th Qtr: Receive approval on the Final EIS from the Federal Highway Administration.