For Immediate Release:
July 5, 2007 |
|
 |
| |
|
|
|
Utility Work Will Close A Section of Central Avenue
Contractor will have road reopened before Labor Day
Knoxville, Tenn.—The Tennessee Department of Transportation announced
today that Central Avenue from Depot Avenue to Fifth Avenue will completely
close for construction at 7 a.m. on Monday, July 9, 2007 until Friday,
August 31, 2007. This is necessary so that contractors can add a sewer line,
storm drains and other utilities.
“The sewer line must be installed15 feet below the surface, in the center of
the road. To ensure safe working conditions at that depth, it is necessary
to lay the slopes back, which expands the width of the cut and takes up more
of the road,” explained John Hunter, TDOT’s SmartFIX40 project manager. “For
that reason, it is not possible for us to complete the work using single
lane closures. It requires a complete closure of the road.”
Due to the upcoming football season and Boom’s Day the contractor will be
working extended hours to have the road reopened by August 31, 2007.
Motorists and pedestrians should use extreme caution in this area and be
aware of construction crews and large equipment. According to traffic count
data, approximately 8,397 vehicles travel this stretch of Central Avenue
daily. During the closure motorists can use Gay Street or Broadway to access
Depot Avenue and the Old City. This is all part of the final phase of the
SmartFIX40 project, scheduled to be complete June 30, 2009.
SmartFIX40 is TDOT’s single most expensive construction project in its
90-year history. Broken into two separate construction contracts, SmartFIX40
has a price tag of approximately $190 million. SmartFIX is an accelerated
construction process used by the department to speed up construction. It
involves closing the primary roadway to allow around-the-clock work that is
uninterrupted by traffic in order to dramatically reduce the time it takes
to complete the project, thereby reducing the long-term inconvenience to
drivers. Using the SmartFIX concept will save over two years of construction
time.
|