(from State Route 21 to Cates Landing Road, Lake County, Tennessee)
Project Timeline:
- Environmental Document Completed June 2008
- Preliminary Design Began October 2008
- Public Design Meeting Held May 28, 2009
- Preliminary Plans Completed September 2009
- Right-of-Way (ROW) Plans Began September 2009
- ROW Plans Completed January 2010
- ROW Appraisal/Acquisition Phase Began April 2010
- ROW Property Owners Informational Public Meeting Held May 18, 2010
Upcoming Events:
- ROW phase completed (ROW completely bought)
- Obtain Necessary Permits
- Prepare Construction Plans
- Authorize Construction Funding
- Let Project
All TDOT projects are developed through a five-step process illustrated below.

We are currently in the Right-of-Way phase for SR-22 acquiring property and arranging relocations.