State Route 22

(from State Route 21 to Cates Landing Road, Lake County, Tennessee)


Project Timeline:

  • Environmental Document Completed June 2008
  • Preliminary Design Began October 2008
  • Public Design Meeting Held May 28, 2009
  • Preliminary Plans Completed September 2009
  • Right-of-Way (ROW) Plans Began September 2009
  • ROW Plans Completed January 2010
  • ROW Appraisal/Acquisition Phase Began April 2010
  • ROW Property Owners Informational Public Meeting Held May 18, 2010

Upcoming Events:

  • ROW phase completed (ROW completely bought)
  • Obtain Necessary Permits
  • Prepare Construction Plans
  • Authorize Construction Funding
  • Let Project

All TDOT projects are developed through a five-step process illustrated below.


TDOT Process

We are currently in the Right-of-Way phase for SR-22 acquiring property and arranging relocations.