Bedford-Moore-Coffee Counties From State Route 64 to North Washington Street
Project Timeline Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur on the improvement of the three (3) sections of S.R. 16 under development: |
|
| Project Schedule for section from SR 64 to SR 276 (not funded for construction, possibly next fiscal year 2013) | |
| Advanced Planning Report | Completed May 25, 1996 |
| Corridor/Design Public Meeting | Completed Sept. 16, 2003 |
| Public Meeting | Completed Feb. 17, 2005 |
| Approval of Final Environmental Document | Completed Feb. 1, 2006 |
| Conduct Right-of-Way Public Meeting | Completed Sept. 12, 2006 |
| Appraisals | Completed March 29, 2009 |
| Property Acquisitions and Relocations | Completed February 15, 2011 |
| Construction Contract | Forecast for late fall 2012 |
| Project Schedule for Section from SR 276 to west of Magnolia Lane. This section has been divided into two new segments in order to sustain funding for construction. | |
| SR 276 to Rippy Ridge Road (not funded for construction; possibly next fiscal year 2013) | |
| Property Acquisitions | Completed March 27, 2009 |
| Property Relocations | Completed January 15, 2010 |
| Construction Contract | Forecast for late fall 2012 |
| Rippy Ridge Road to west of Magnolia Lane (funded for construction in fiscal year 2010) | |
| Construction Contract | Contract awarded April 30, 2010 |
| Project Schedule for section from Moore/Coffee Co. Line to N. Washington St. | |
| Roadway opened for traffic | March 9, 2007 |